The application of wood flooring in decoration is more and more extensive, and it is favored by owners. Its color gives people a natural, environmentally friendly, warm and practical feeling. Especially in winter, compared with the cold floor tile Wood Floor is more attractive. The advantages of wood flooring are reflected in six aspects: durability, environmental protection, good foot feeling, warm in winter and cool in summer, beautiful and natural, and natural fragrance. The advantages of wood flooring are always so exciting, but do you know the construction standards and processes of wood flooring? Next, Jing Mujun will take you into the construction site to see what processes are available for wood flooring, as well as wood flooring installation, skirting installation and finished product protection processes.

. ground floor

Description of process practices:

1, the floor base clean, no water mud residue, floating dust, oil, landing dust, etc.

2. If there is floor heating, install the insulation cushion and duct first.

. punching bar

Description of process practices:

1. Detect the horizontal one-meter line and pop up the ground completion line.

2. Fully wet the ground and sweep the cement slurry.

3, plastering cake 500*500, horizontal and vertical direction is 1200*1500.

4.1:3 cement mortar shall be used as ground leveling bar with spacing of 1500mm.

5, after the completion of the water maintenance (12 hours).

. leveling layer

1.1:3 cement mortar shall be used for ground leveling. Due to the different construction time between the punching bar position and the leveling layer, the height of the leveling layer is slightly 2-3mm higher than that of the cramp point, so as to ensure that all ground heights are consistent after drying.

2. The ground is finally calendered, and water drenched for one week after completion. During this period, other types of work are not allowed to enter the construction, so as not to damage the ground and crack the ground.

. moisture-proof mat

Description of process practices:

1. Before laying the moisture-proof cotton mat, ensure that the cement floor is dry and free of floating dust, residual mud, garbage, cement blocks, etc. During acceptance, stamp the cement floor with your feet, including no floating dust and dust at the corners. Avoid dust from the foot line or corner when stepping on the corner after completion acceptance.

2. Spread the damp-proof pad fully. Use sealing glue and other adhesive tapes at the interface to adhere. The damp-proof pad shall not be damaged or cracked, and the interface is not overlapped.

3, moisture-proof mat paving along the wall around 200-300mm.

. Installation of 5. wood floor

Description of process practices:

1. Pay attention to the color difference of the product when installing the wooden floor. It is better to find someone to select the floor before starting work. Classify the floor with color difference. The floor with dark color and small quantity shall be installed at the corner or the position covered by furniture in the future.

2, wood floor installation against the wall position need to reserve expansion joints (to foot line thickness should be covered), expansion joints need to install spring buckle, buckle distance 600mm.

3, there is a threshold stone, wood floor installation pay attention to flush with the threshold stone.


. Installation of 6. skirting line

Description of process practices:

1. Pay attention to the color difference at the interface when installing the foot line (especially the solid wood foot line).

2. Pay attention to the straightness of the installation position of the wall ground line before installing the ground line (the error is not more than 3mm).

3. Pay attention to the smoothness of the interface when installing the ground-foot line, and do not feel concave and convex by hand.

. Finished Product Protection

Description of process practices:

1. Comprehensively check the quality of wood floor installation (whether there is warping, dust on corners, looseness, etc.).

2. Clean the garbage and dust after installation.

3. Use ordinary moisture-proof cotton or non-woven fabric as cushion layer.

4, the use of more than 8mm thick corrugated paper (coil) pavement, interface lap 3-5cm, use strong sealing glue adhesion (note, foot line corners with ordinary roll glue adhesive, check every half month, so that adhesive shall not adhere to the surface of the product, resulting in future cleaning problems).


Home

Product

Phone

About Us

Inquiry

We will contact you immediately

Fill in more information so that we can get in touch with you faster

Privacy statement: Your privacy is very important to Us. Our company promises not to disclose your personal information to any external company with out your explicit permission.

Send